Chestnut Parkway - Phase 1B

Description

This project includes the construction of approximately 1,200 feet of asphalt roadway with divided median, concrete curb and gutter, and storm drainage from the existing Chestnut Parkway to US Highway 74. Additional work along US Highway 74 includes, installing a right turn lane, relocating a left-over, and relocating approximately 820' of 16" water main.

Town Council awarded the contract to DeVere Construction Company, Inc. in the amount of $1,415,527.37 (Base Bid and Alternate No. 1).

Project Data

Advertisement
Addendum 1
Bid Results
Bid Tabs 

Project Completion

Substantial Completion - December 2014

Project Manager

Todd Huntsinger